Construction Photos

Placement of clear stone on the east south pond. This photo was captured on April 4, 2024.

Ongoing work at Concession Road 7. This photo was captured on March 25, 2024.

Moving topsoil along Concession Road 7. This photo was captured on March 25, 2024.

This photo was captured on February 13, 2024.

Placement of silt fencing along Concession Road 7. This photo was captured on February 13, 2024.

Paving underway at the South-East-West ramp. This photo was captured on November 22, 2023.

Photo showing the completion of excavation and grading, as well as placement of Granular A and B. This photo was captured on November 22, 2023.

Construction of the bridge deck over Highway 6 / Hanlon Expressway. This photo was captured on November 15, 2023.

Construction of the South-East-West ramp. This photo was captured on October 18, 2023.

Placement of the Granular A material on the East-North ramp. This photo was captured on October 12, 2023.

Photo of concrete pouring at the North parapet wall. This photo was captured on October 4, 2023.

Photo of the North parapet wall. This photo was captured on October 4, 2023.

Placement of Granular A on the North-East/West ramp. This photo was captured on September 29, 2023.

Placement of Granular A on the North-East/West ramp. This photo was captured on September 29, 2023.

The Dufferin Construction Team completing the second deck pour. This photo was captured on August 31, 2023.

The Dufferin Construction Team completing the second deck pour. This photo was captured on August 31, 2023.

Deck pour. This photo was captured on August 25, 2023.

Deck pour. This photo was captured on August 25, 2023.

Granular B placement on the West / South ramp at the Highway 6 / Hanlon Expressway Midblock Interchange. This photo was captured on August 14, 2023.

Placement of granular material on the North East/West ramp at the Highway 6 / Hanlon Expressway Midblock Interchange. This photo was captured on July 28, 2023.

Launching the girders and working on the bridge deck. This photo was captured on July 24, 2023.

Launching the girders and working on the bridge deck. This photo was captured on July 24, 2023.

A photo of the granular material being crushed on site. This photo was captured on July 7, 2023.

Concrete pour for the columns in the center median of Highway 6/Hanlon Expressway. This photo was captured on June 13, 2023.

Concrete pour for the wing wall on the west abutment. This photo was captured on June 6, 2023.

Pile driving completed in the centre median. This photo was captured on May 23, 2023

Dufferin Construction continues to backfill at the east abutment. This photo was captured on May 17, 2023.

Pile driving in the centre median. This photo was captured on May 17, 2023.

Pouring concrete at the west abutment. This photo was captured on April 20, 2023.

Dufferin Construction forming the west abutment. This photo was captured on April 20, 2023.

Dufferin Construction forming the east abutment. This photo was captured on April 20, 2023.

Pouring the concrete footing on the west side of Highway 6/Hanlon Expressway. This photo was captured on April 3, 2023.

Footing reinforcement on the east side of Highway 6/Hanlon Expressway. Photo captured on April 3, 2023.

Silt fencing along the property line on the west side of Highway 6/Hanlon Expressway. Photo captured on April 3, 2023.

Photo from the site, taken on March 23, 2023.

Photo showing the piles on the east abutment. This photo was captured on March 23, 2023.

Formwork and bottom rebars on the west side of Highway 6/Hanlon Expressway. This photo was taken on March 20, 2023.

Photo showing the piles on the east abutment. This photo was captured on March 13, 2023.

Photo showing the work site on the west side of Highway 6. This photo was captured on March 13, 2023.

Driven piles along the west side of Highway 6. This photo was captured on February 27, 2023

Photo showing test pit investigations between Concession Road 7 and Highway 6. This photo was captured on February 21, 2023.

Clearing activities for the Midblock Interchange. Photo captured on February 3, 2023.

Continued clearing activities for the Midblock Interchange. Photo captured on February 3, 2023.